Vendor: PMI
Certifications: PMI Certifications
Exam Name: PMI Risk Management Professional (PMI-RMP)
Exam Code: PMI-RMP
Total Questions: 580 Q&As ( View Details)
Last Updated: Mar 18, 2025
Note: Product instant download. Please sign in and click My account to download your product.
VCE
PMI PMI-RMP Last Month Results
PMI-RMP Q&A's Detail
Exam Code: | PMI-RMP |
Total Questions: | 580 |
Single & Multiple Choice | 577 |
Fill in the Blanks | 3 |
CertBus Has the Latest PMI-RMP Exam Dumps in Both PDF and VCE Format
PMI-RMP Online Practice Questions and Answers
Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?
A. Internal risk management strategy
B. Contingent response strategy
C. External risk response
D. Expert judgment
You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?
A. Parkinson's Law
B. Mitigation
C. Avoidance
D. Lag Time
You work as a project manager for TechSoft Inc. You are preparing to plan risk responses for your project with your project team. How many risk responses are available for a positive risk event in the project?
A. Three
B. Four
C. Seven
D. One
The project manager of a project in trouble actively participates in a project risk assessment. After the assessment is complete, the project manager receives the final results.
What is the best recommended action to be taken from this point onward?
A. Schedule a meeting and present the assessment results.
B. Use the assessment results in the day-to-day management of project risks.
C. Schedule a meeting with the project sponsor and discuss the assessment results.
D. Use the assessment results to review the project hand over plan to operations.
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.
What should the risk manager do next?
A. Add only the threats to the risk register
B. Utilize different tools to identify the risks
C. Plan risk responses to the threats
D. Update the risk register with the identified risks
Add Comments
Passed full scored. I should let you know. The PMI-RMP exam dump is very good, valid and accurate.
I'm very happy that I have passed the PMI-RMP exam with high score. I will share this good dumps with my friend. You can trust on it.
This dumps is valid, and this dumps is the only study material i used for this exam. Surprisingly i met the same question in the exam, so i passed the exam without doubt. Thanks for this dumps and i will recommend it to my friends.
update quickly and be rich in content, great dumps.
There are many new questions in the dumps and the answers are accurate and correct. I finished my exam with high score this morning, thanks very much.
Recommend this PMI-RMP exam dump to you strongly, really useful and convenient.
thanks god and thank you all. 100% valid. you can trust on it.
There are so many new questions in the latest update. You can trust on this. Good luck to you all, guys.
The new questions in the exam are not the new questions for me because I have met them when I used this material . So there is no doubt that I have passed the exam with high score. Recommend this material strongly.