Certbus > PMI > PMI Certifications > PMI-RMP > PMI-RMP Online Practice Questions and Answers

PMI-RMP Online Practice Questions and Answers

Questions 4

Which risk response is acceptable for both positive and negative risk events?

A. Transferring

B. Acceptance

C. Sharing

D. Enhancing

Browse 580 Q&As
Questions 5

You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure:

If Risk D happens in this project, how much will be left in the contingency reserve?

A. $440,000

B. $233,500

C. $258,500

D. $243,500

Browse 580 Q&As
Questions 6

Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?

A. -$217,500

B. 20 percent

C. -$174,000

D. -$269,000

Browse 580 Q&As
Questions 7

What approach can a project manager use to improve the project's performance during qualitative risk analysis?

A. Focus on near-term risks first.

B. Create a risk breakdown structure and delegate the risk analysis to the appropriate project team members.

C. Focus on high-priority risks.

D. Analyze as many risks as possible regardless of who initiated the risk event.

Browse 580 Q&As
Questions 8

You are interviewing members of a project team to test their understanding of the assigned risk responses as risk owners. You and the project manager are working together to evaluate the risk responses to determine their effectiveness in the project. What project management technique are you performing with the project manager in this scenario?

A. Risk audits

B. Stakeholder analysis as the project team is a stakeholder

C. Risk identification with the project team

D. Risk analysis

Browse 580 Q&As
Questions 9

The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has an overall project risk that exceeds the risk levels documented in the risk management plan.

What would be the best course of action for the company to take with the project based on its current scope?

A. Monitor ongoing risks closely for any major changes.

B. Perform a Monte Carlo simulation to understand possible risk outcomes.

C. Cancel the project, as the overall level of risk remains unacceptable.

D. Conduct a stakeholder meeting to validate stakeholder risk appetite.

Browse 580 Q&As
Questions 10

A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?

A. Risk register

B. Risk response plan

C. Risk management plan

D. Risk identification plan

Browse 580 Q&As
Questions 11

The risk management process can be defined as which of the following?

A. Iterative through the planning phase

B. Baselined at the beginning of execution

C. Iterative throughout the entire project

D. Updated in the execution phase

Browse 580 Q&As
Questions 12

When using the risk register to manage the cost risk analysis, which of the following models the way correlation arises, and avoids the need to estimate the correlation coefficients?

A. Risk Monte Carlo analysis

B. Risk driver method

C. Risk scatter diagram

D. Risk RACI matrix

Browse 580 Q&As
Questions 13

Which statement describes the risk portrayed on the risk matrix heat map below?

A. The risk has a probability of 60% of occurrence and a medium impact rating.

B. The risk has a probability of 40% of occurrence and a high impact rating.

C. The risk has a high impact and probability of occurring.

D. The risk has a low probability and high impact rating.

Browse 580 Q&As
Questions 14

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

A. Include all stakeholders in the project's governance.

B. Communicate response strategies to all stakeholders.

C. Ignore any risks beyond stakeholders' tolerance.

D. Consider stakeholders' positions and opinions regarding the project's output.

Browse 580 Q&As
Questions 15

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

A. When the forecast activity date has been met or exceeded

B. When the stakeholders agree a risk is no longer applicable

C. When the risk has been realized and can no longer happen again

D. When iterative data analysis determines the risk is not applicable

Browse 580 Q&As
Questions 16

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

A. Provided regular training to the risk owners for plan implementation

B. Determined risk triggers and thresholds in the risk response plan

C. Increased communications to influence stakeholder risk responses

D. Updated the project schedule, adding risk owner implementation tasks.

Browse 580 Q&As
Questions 17

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

A. Industrial studies

B. Commercial risk databases

C. Organizational process assets (OPAs)

D. Enterprise environmental factors (EEFs)

Browse 580 Q&As
Questions 18

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

A. Applying modern risk management techniques.

B. Aligning to project constraints and priorities.

C. Ensuring risk response strategies mitigate all risks.

D. Minimizing implementation costs.

E. Obtaining stakeholder acceptance

Browse 580 Q&As
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP)
Last Update: Mar 18, 2025
Questions: 580 Q&As

PDF

$49.99

VCE

$55.99

PDF + VCE

$65.99