A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is the project team demonstrating?
A. Storming
B. Performing
C. Conforming
D. Forming
The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?
A. The project will be behind schedule and over-budget.
B. The project will be on schedule but over-budget.
C. The project will be on schedule and on-budget.
D. The project will be behind schedule and on-budget.
Which of the following would be the MOST important objective of a kick-off meeting? (Select Two).
A. To educate team members on what will be expected
B. To give official notification for the project
C. To inform the project sponsor on what will be expected
D. To create a work breakdown structure (WBS)
E. To develop the statement of work (SOW)
Which of the following is a benefit of a work breakdown structure (WBS)?
A. It can determine the amount of progress on the project.
B. It can quickly identify the projects major deliverables and underlying activities with graphical representation.
C. It can quickly identify the probability and impact of project risks.
D. It allows a real time analysis of actual project costs compared to the project baseline to determine the project variances.
An ongoing project requires several parts manufactured at an outside vendor. If the vendor has sufficient quantity and can still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days. Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the PERT method, which of the following is the correct time estimate for a parts delivery?
A. 10 days
B. 11 days
C. 21 days
D. 36 days
Add Comments
Thanks a lot and good luck to everybody.
i have passed today, All the questions are from their dumps, thanks for this dumps.
A valid dumps. It helped me pass the exam in short time. Thanks a million.
The content of this dumps is rich and complete, you can find that all the answers of questions from this dumps. Very useful.
In the morning i received the good news that I have passed the exam with good marks. I'm so happy for that. Thanks for the help of this material.
Absolutely valid. i passed today. You are the best. Thanks so much.
Very good JK0-017 dumps, take full use of it, you will pass the exam just like me.
There are so many new questions in the latest update. You can trust on this. Good luck to you all, guys.
Passed today......... Thanks a lot guys! I only Study your manuals and sims. Valid dumps! Good luck to u all~!
Passed my exam today. Great job.Thanks this dumps.