A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
A. Performing
B. Adjourning
C. Forming
D. Norming
A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?
A. Use an on-premises project management scheduling tool.
B. Limit access to members of the project team.
C. Mandate overtime to get the project completed sooner.
D. Ensure all team members have signed a non-disclosure agreement.
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
A. Trigger the contingency plan and communicate with the stakeholders.
B. Work with the functional managers to create a work-around.
C. Submit a change request to the change control board.
D. Transfer the risk by hiring a new vendor who was successful on a previous project.
E. Set up an escalation meeting with the sponsor.
A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?
A. Train the team members.
B. Assess the resource pool.
C. Develop a QA plan.
D. Create RACI matrix.
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the
project manager realizes the candidate has a non-compete agreement from the previous employer.
Which of the following should the project manager do?
A. Withdraw the offer to the candidate and raise this as a risk.
B. Ignore a potential lawsuit since this is a critical project.
C. Use a third-party company for the contract to legally avoid responsibility.
D. Have a meeting with the project sponsor to discuss the situation.
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
A. Lessons learned
B. Risk analysis
C. Removing resources
D. Acquiring resources
E. Statement of work sign-off
F. Stakeholder analysis
G. Removing access
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
A. Communicate with the affected stakeholders.
B. Initiate a formal change request to modify the cost
C. Adjust the scope to stay within the cost.
D. Set a new cost using a lightweight estimation method.
Which of the following software programs would be best to use to store information related to business transactions?
A. Record management system
B. Customer relationship management
C. Enterprise resource planning
D. Content management system
The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit.
Which of the following actions should the project manager take?
A. Initiate change control.
B. Follow communications plan.
C. Manage project quality.
D. Prepare a performance report.
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
A. Rollback plan
B. Downtime stage
C. Maintenance window
D. Validation checks
A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?
A. Monte Carlo simulation
B. Root cause analysis
C. Quantitative risk analysis
D. Risk response analysis
Which of the following is the best example of a breach of physical security?
A. System user IDs being used by multiple individuals
B. Printers that do not request user authentication
C. Developers having full access to both development and production environments
D. Project documentation that is only kept on a removable device
To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?
A. Process moving
B. Brainstorming
C. Interview
D. Focus group
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite
easily without affecting the completion date.
Which of the following should the project manager do first?
A. Escalate the change to the CCB.
B. Review the requested change.
C. Document the change recommendations.
D. Validate the implementation of the requested change.
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?
A. Update the scope management plan.
B. Modify the project baselines.
C. Implement change control management.
D. Inform the stakeholders of the issue.