What is an activity that is performed at the end of the Realize phase?

A. Run the user acceptance test

B. Perform cutover simulation

C. Load data into production system

D. Provision development system

Browse 40 Q&As
Questions 5

What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 2 correct ans-wers to this que-stion.

A. Project management expertise

B. Technology and architecture expertise

C. Business process expertise

D. Process benchmarking expertise

Browse 40 Q&As
Questions 6

Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?

A. Leveraging effort estimates for similar User Stories from another Scrum team

B. Detailed bottom-up estimates that break each User Story into shorter tasks

C. Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team

D. Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days

Browse 40 Q&As
Questions 7

Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct ans-wers to this que-stion.

A. Detailed Design - Business Process

B. End User Learning Needs Analysis

C. Learning Content

D. Change Management Roadmap

E. Project Plan

Browse 40 Q&As
Questions 8

What is the purpose of "Scrum of Scrums"?

A. To run an integration meeting across the various teams

B. To create an alternative Scrum process for larger teams

C. To conduct a regular review of risk and issues

D. To gather requirements from business users

Browse 40 Q&As
Questions 9

In which phase do you create "an ordered list of everything that is known to be needed in the product"?

A. Prepare

B. Discover

C. Realize

D. Explore

Browse 40 Q&As
Questions 10

What is the purpose of the scrum board? Note: There are 2 correct ans-wers to this que-stion.

A. To represent the scrum team setup

B. To visualize scrum team progress

C. To represent the work

D. To manage the scrum resources load

Browse 40 Q&As
Questions 11

Which of the following are benefits of using ready-to-use content? Note: There are 2 correct ans-wers to this que-stion.

A. Predictable results

B. Maximized total cost of ownership

C. Exhaustive solution documentation

D. Fast time-to-value

Browse 40 Q&As
Questions 12

What accelerator can help you document the configuration definition in the Explore phase?

A. Data definition

B. Business Driven Configuration Questio-nnaire

C. Backlog template

D. Business Blueprint document

Browse 40 Q&As
Questions 13

What is the result of fit-to-standard workshops?

A. Detailed assessment of customer's current business processes

B. Preparation of standard test cases and test scripts for end users

C. Prioritization of the requirements backlog by the team

D. Confirmation solution fit and identification of delta requirements

Browse 40 Q&As
Questions 14

What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct ans-wers to this que-stion.

A. Sprint duration between 1 week to 4 weeks.

B. Adjust sprint duration based on team availability.

C. Set variable sprint duration based on work.

D. Establish fixed duration of each sprint.

Browse 40 Q&As
Questions 15

What information does the Scrum team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct ans-wers to this que-stion.

A. Definition of Done

B. Number of backlog user stories

C. Anchor user story in the backlog

D. Definition of Ready

Browse 40 Q&As
Questions 16

What are the core capabilities in SAP Cloud ALM for operations? Note: There are 3 correct ans-wers to this que-stion.

A. Monitoring

B. License management

C. Event and alert management

D. Operation automation

E. Upgrade analysis

Browse 40 Q&As
Questions 17

What are the SAP Cloud ALM Implementation capabilities? Note: There are 2 correct ans-wers to this que-stion.

A. Check data quality prior to migration

B. Perform implementation activities

C. Monitor project performance centrally

D. Natively built in test automation

Browse 40 Q&As
Questions 18

Which tools can SAP Cloud ALM leverage for project tasks? Note: There are 2 correct ans-wers to this que-stion.

A. SAP Readiness Check

B. SAP Central Business Configuration

C. SAP Solution Manager

D. SAP Signavio Process Navigator

Browse 40 Q&As
Exam Code: E_ACTAI_2403
Exam Name: SAP Certified Specialist - Project Manager - SAP Activate for Agile Implementation Management
Last Update: Mar 15, 2025
Questions: 40 Q&As

PDF

$49.99

VCE

$55.99

PDF + VCE

$65.99