Certbus > SAP > SAP Certifications > C_TS413_2021 > C_TS413_2021 Online Practice Questions and Answers

C_TS413_2021 Online Practice Questions and Answers

Questions 4

You are analyzing the data transfer of the cost center of an equipment. What are the possible data origins? Note: There are 2correct answers to this question.

A. The reference functional location of the superior functional location

B. The individual maintenance of the cost center in the equipment master record

C. The cost center of the related maintenance work center

D. The cost center of the superior equipment

Browse 87 Q&As
Questions 5

Which statement is correct when planning maintenance work thatis to be carried out by an external company?

A. In the control key assigned to the order operation, the "Service"indicator must always be activated.

B. A service master record must always be assigned to the external order operation.

C. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet.

D. If you assign a control key for an external order operation, theactual values must always be entered as a goods receipt in the system.

Browse 87 Q&As
Questions 6

What is the correct receiver object type for the settlement of arefurbishment order?

A. The fixed asset

B. The cost center

C. The material

D. The WBS element

Browse 87 Q&As
Questions 7

A piece of equipment cannot be linked to a material. Determine whether this statement is true or false.

A. True

B. False

Browse 87 Q&As
Questions 8

Which valuation category do you use to refurbish a material?

A. Origin

B. Retail

C. Condition-based

D. In-house/external procurement

Browse 87 Q&As
Questions 9

You cancel the technical completion of a work order. What are theeffects? Note: There are 2 correct answers to this question.

A. Open purchase orders are recompiled.

B. Openreservations are recompiled.

C. Referenced notifications are put In Process again.

D. Open purchase requisitions are recompiled

Browse 87 Q&As
Questions 10

Which objects have been enhanced with lineardata in maintenance processes? Note: There are 3 correct answers to this question.

A. Work order confirmation

B. Maintenance plan header

C. Measurement document

D. Maintenance plan item

E. Equipment task list

Browse 87 Q&As
Questions 11

You want toassign components to an equipment task list. There isno BOM assigned to the equipment. What is the prerequisite for using the free assignment of material?

A. Free assignment of material is always possible without any prerequisites.

B. Assign the header material of a material BOM to the equipmenttask list header.

C. Assign the header material of a material BOM as assembly to atask list operation.

D. Assign the BOM usage for free assignment of material in Customizing.

Browse 87 Q&As
Questions 12

The planner adds non-stock material in a released maintenance order. Which of the following statements regarding the purchasing process are correct? Note: There are 3 correct answers to this question.

A. The maintenance order can be set to TECO before the invoice is created.

B. A purchase order is created automatically as soon as the order is saved.

C. A purchase requisition can be created automatically as soon asthe the order is saved.

D. A goods receipt can be posted after the maintenance order is technically completed

E. A goods receipt can ONLY be posted for a maintenance order with status REL.

Browse 87 Q&As
Questions 13

You want to have several plan dates calculated in a maintenance plan. Which scheduling parameter do you use?

A. Call horizon

B. Lead float

C. Scheduling period

D. Scheduling indicator

Browse 87 Q&As
Questions 14

Which SAP UI technology is used for the technicianls job list?

A. SAP GUI for Windows

B. Web Dynpro

C. SAPUI5

D. SAP GUI for HTML

Browse 87 Q&As
Questions 15

Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 3correct answers to this question.

A. Change the planned costs.

B. Change the settlement rule.

C. Lock or unlock the order.

D. Create an invoice receipt for delivered materials.

E. Update the estimated costs

Browse 87 Q&As
Questions 16

Which material type is the best choice if you only want to create a structure element within the BOM?

A. Spare part (ERSA)

B. Maintenance assembly (IBAU)

C. Non-valuated material (UNBW)

D. Operating supplies (HIBE)

Browse 87 Q&As
Questions 17

In which component do you have to perform most of theconfiguration to set up SAP Asset Manager?

A. SAP Cloud Platform

B. SAP ERP

C. SAP Mobile Platform

D. SAP S/4HANA

Browse 87 Q&As
Questions 18

Which of the following statements about breakdown maintenanceare correct? Note: There are 3 correct answers to this question.

A. More than one operation must always be maintained in themaintenance order.

B. Notifications are used for documentation of technical findingsand activities performed.

C. Maintenance orders can be created as immediate orders without any planning.

D. Orders always need to be combined with notifications

E. Ordersand notifications can be utilized in combination

Browse 87 Q&As
Exam Code: C_TS413_2021
Exam Name: SAP Certified Associate - SAP S/4HANA Asset Management
Last Update: Mar 13, 2025
Questions: 87 Q&As

PDF

$49.99

VCE

$55.99

PDF + VCE

$65.99