Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
A. Network profile
B. Project profile
C. Parameters for the network type
D. Network type
How can you update the degree of processing for an activity?
A. By using results analysis
B. By changing the activity
C. By scheduling the activity
D. By confirming the activity
For which objects can billing plans be created? Note: There are 2 correct answers to this question
A. WBS elements
B. Project definition
C. Sales order items
D. Milestones
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note: there are 3 correct answer for this question.
A. You can create several WBS elements per level.
B. A new work breakdown structure must contain up to 10 levels.
C. A WBS element of the new project can be assigned to a different project definition.
D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
E. The WBS structure can contain several level 1 WBS element,
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
A. An activated Scheduling indicator in the control key of the internal processing activity
B. Whether the work for the internal activity is greater than its duration
C. The unit (for example, hour, day) of the field Normal Duration field of the activity
D. The relationships between activity elements
E. The factory calendar in the work center used for the internal processing activity
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
A. Maintain subordinate internal activity elements assigned to other work centres
B. Increase the capacities of the work center in the project planning board.
C. Trigger automatic capacity leveling inside the project planning board
D. Shift activities backward or forward on the time axis where more capacities are available
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question
A. Duration
B. Activity type
C. Work
D. Profit center
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
A. Float time can be negative
B. Activities with the time constraint "Must start on" always have a negative float time
C. The float time of WBS elements is calculated by extrapolation
D. By default, critical activities have a float time, which is less than or equal to zero
E. The maximum size of a free float is as large as the total float of an activity
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
A. Material master
B. Network activity
C. WBS element
D. BOM item
You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?
A. Vendor selection-> Purchase order handling-> Invoice receipt-Purchase order monitoring-> Goods receipt
B. . Credit limit check-> Acceptance of performed services-> Vendor selection-> Purchase order handling-> Purchase order monitoring-> Goods receipt-> invoice receipt
C. Vendor selection-> Purchase order creation-> Service entry sheet creation-> Service entry sheet approval
D. Vendor selection-> Purchase order handling-> Purchase order monitoring-> Goods receipt
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
A. Basic dates
B. Forecast dates
C. Baseline dates
D. Planned dates
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.
Note : there are 3 correct answers for this question.
A. Display of production orders assigned to WBS element.
B. Display of plant maintenance orders for activities.
C. Display of project cost plan.
D. Display of project-relevant purchase order.
E. Using specific color management for Gantt Chart.
To which object can you assign a factory calendar?
A. Material component
B. Network header
C. Relationship
D. Milestone
What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question
A. Project simulations allow posting of actual data
B. Project simulations can be created without using an operational project as a template
C. Project simulations can be used to plan structures and costs
D. Project simulations can create purchase requisitions
E. Multiple project simulations can be used simultaneously
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
A. Individual overview capacity requirements
B. Capacity load work center view
C. Extended capacity evaluation
D. Structure overview