Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question

A. Schedule kick-off workshop

B. Conduct Scope Validation

C. Confirm Integration prerequisites

D. Perform Fit/Gap Analysis

Browse 198 Q&As
Questions 5

When is the Quality System upgraded to the latest release?

A. Don the Release to Customer (RTC) date

B. The second weekend after the RTC date

C. The first weekend after the RTC date

D. The third weekend after the RTC date

Browse 198 Q&As
Questions 6

Arrange the following in the correct sequence of steps followed for a Fit to Standard workshop. Please choose the correct answer.

A. Demonstrate Business Scenarios and Concepts, Review Best Practice Process Flow, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps

B. Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Discuss how the process fit with customer requirements, Identify gaps, Identify required configuration, Enable customer on execution of scenarios

C. Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps

D. Discuss how the process fit with customer requirements, Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Enable customer on execution of scenarios, Identify gaps

Browse 198 Q&As
Questions 7

What are some of the training tools / resources available in SAP Learning Hub?

A. Live Sessions in SAP Learning Rooms

B. Learning Center App

C. SAP Learning Rooms

D. SAP Best Practice Business Processes

E. SAP Learning Journeys

Browse 198 Q&As
Questions 8

In which tools can the project team across the SAP Activate Methodology content including accelerators?

There are 2 correct answers to this question.

Response:

A. SAP Community Network

B. Roadmap Viewer

C. SAP Jam

D. SAP Service Marketplace

Browse 198 Q&As
Questions 9

In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the

customer?

Please choose the correct answer.

Response:

A. Explore

B. Deploy

C. Realize

D. Prepare

Browse 198 Q&As
Questions 10

What is the objective of a sprint retrospective meeting?

Please choose the correct answer.

Response:

A. Define the stakeholder management approach

B. Review and prioritize the backlog

C. Provide formal feedback to the project manager

D. Improve the SCRUM process

Browse 198 Q&As
Questions 11

Who determines the priority of user stories in the backlog of an Agile project?

Please choose the correct answer.

Response:

A. Project Manager

B. Project Team

C. SCRUM Master

D. Product Owner

Browse 198 Q&As
Questions 12

What is SAP Activate?

Please choose the correct answer.

Response:

A. A step-by-step instruction on how to remove from SAP best practices to your custom solution

B. A methodology for each of the deployment modes (cloud , on-premise, hybrid)

C. A bundle of ASAP , SAP Launch , and Rapid Deployment Solutions

D. A combination of SAP best practices , methodology, and guided configuration

Browse 198 Q&As
Questions 13

Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?

A. User stories are in a ready state for NO more than the first three sprints

B. Project scope and planning are completed and final

C. Timelines of the sprint may differ due to the workload

D. Go-live scope is fixed on the first of January the following year

Browse 198 Q&As
Questions 14

In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer.

A. Prepare

B. Explore

C. Realize

D. Deploy

Browse 198 Q&As
Questions 15

How can organizations closely connect subsidiaries with headquarters to run end-to-end business scenarios?

A. With a cloud solution

B. With a 2-tier ERP solution

C. With a 4-tier ERP solution

D. With a fully functional ERP solution

Browse 198 Q&As
Questions 16

What does "de-coupling extensions" mean in SAP S/4HANA Cloud?

A. Extensions will not clash with quarterly release upgrades

B. Extensions are separated from the stable system of records.

C. Extensions are applied with modifications in the HANA database

D. Extensions could conflict with future release enhancements

Browse 198 Q&As
Questions 17

What types of extensibility are supported directly in the SAP S/4HANA Cloud solution?

A. In-App (Key User) Extensibility

B. Classic Extensibility

C. Side-by-Side Extensibility

D. Managed Extensibility

Browse 198 Q&As
Questions 18

What are some characteristics of the "Cloud" mindset?

A. Make the company fit the software

B. Heavy customizations and modifications

C. Business blueprint phase

D. Workarounds and light extensions

E. Fit-to-Standard workshops

F. Make the software fit the company

Browse 198 Q&As