Certbus > PMI > PMI Certifications > PMI-SP > PMI-SP Online Practice Questions and Answers

PMI-SP Online Practice Questions and Answers

Questions 4

Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project. The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?

A. The schedule performance is better than expected.

B. The schedule performance is right on target.

C. The cost performance is better than expected.

D. The schedule performance is below expectation.

Browse 323 Q&As
Questions 5

Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

A. The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

B. The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.

C. The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

D. The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

Browse 323 Q&As
Questions 6

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

A. Records Management System

B. Performance reporting

C. Inspection and Audit

D. Payment System

Browse 323 Q&As
Questions 7

In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

A. Estimate activity resources

B. Define activities

C. Control schedule

D. Develop schedule

Browse 323 Q&As
Questions 8

You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?

A. Issue report

B. Exceptions report

C. Variance analysis

D. Performance report

Browse 323 Q&As
Questions 9

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

A. Ideas to action

B. Problem definition

C. Problem solution generation

D. Solution action planning

Browse 323 Q&As
Questions 10

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

A. 0.76

B. 0.85

C. 0.80

D. 0.92

Browse 323 Q&As
Questions 11

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

A. -$98,217.78

B. -$44,198

C. $441,025.64

D. $243,219.78

Browse 323 Q&As
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional (PMI-SP)
Last Update: Mar 18, 2025
Questions: 323 Q&As

PDF

$49.99

VCE

$55.99

PDF + VCE

$65.99