Certbus > SAP > SAP Certifications > C_TPLM22_64 > C_TPLM22_64 Online Practice Questions and Answers

C_TPLM22_64 Online Practice Questions and Answers

Questions 4

In which of the following ways Open PS allows you to exchange data directly with MS project? There are 3 correct answers to this question. Response:

A. Create a project in MS project from an SAP PS project

B. Transfer a project from MS project to SAP PS

C. Download MS project and Upload to SAP PS

D. Reconcile data from a project in Microsoft Project with a project in SAP PS

Browse 234 Q&As
Questions 5

Which account category is used for account assignment of orders, which includes network headers,

network activities, maintenance orders, internal orders and manufacturing orders? Please choose the

correct answer.

Response:

A. C

B. B

C. F

D. E

Browse 234 Q&As
Questions 6

If the available user-definable fields do not satisfy your requirement, you have an option to develop

additional fields for which of the following.

There are 2 correct answers to this question.

Response:

A. WBS elements

B. Project definition

C. Activities

D. Tasks

Browse 234 Q&As
Questions 7

You have created a network with successive activities. After scheduling the network, the Gantt chart

shows that every activity has the same earliest start and earliest finish date as the network header. What

could be the reason? Please choose the correct answer.

Response:

A. The control key is set to no scheduling.

B. The scheduling type is set to capacity requirements only.

C. The normal duration of each activity is missing.

D. There is a loop in the network.

Browse 234 Q&As
Questions 8

What are the different views available for capacity planning and work center planning? There are 2 correct answers to this question.

A. Work center view

B. Periodic view

C. Capacity planning view

D. Project view

Browse 234 Q&As
Questions 9

Which of the following helps you to adjust cost planning to changing circumstances during the execution

phase of the project?

Please choose the correct answer.

A. Progress analysis

B. Overhead costs

C. Interest forecast

D. Cost forecasts

Browse 234 Q&As
Questions 10

Which function allows you to check consistency of the dates within the project structure with or without taking activities into account? Please choose the correct answer.

A. Sets of dates

B. Planning methods

C. Check dates

D. Extrapolate

Browse 234 Q&As
Questions 11

Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element? Please choose the correct answer.

A. Billing plan in project billing elements

B. Manual planning in billing elements in the project structure

C. Hierarchical billing plan

D. Sales order planning

Browse 234 Q&As
Questions 12

Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks. How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time? Please

choose the correct answer.

A. Actions

B. Claim management

C. Safety measures

D. Status management

Browse 234 Q&As
Questions 13

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing? There are 2 correct answers to this question.

A. Create a billing plan assigned to a sales order item.

B. Set up percentage of completion for milestones.

C. Activate indicator sales document date for milestones.

D. Create a billing plan assigned to a WBS element.

E. Activate milestone functions.

Browse 234 Q&As
Questions 14

In your project, you choose internal activities to confirm actual dates. After you partially confirmed an

internal activity, you want that the actual start will be considered for the calculation of the earliest

scheduled dates. How can you implement this?

Please choose the correct answer.

A. Deactivate the shift order indicator in Parameters for Network Scheduling.

B. Activate the shift order indicator in Parameters for Network Scheduling.

C. Activate the actual date consider indicator in Parameters for Network Scheduling.

D. Deactivate actual date consider indicator in Parameters for Network Scheduling.

Browse 234 Q&As
Questions 15

The determination of the settlement profile and result analysis key is based on WBS-operative indicators

for which of the following? There are 2 correct answers to this question.

Response:

A. Billing element

B. Settlement rule

C. Operative rule

D. Account assignment

Browse 234 Q&As
Questions 16

Which business functions from the following are supported by network activities? There are 3 correct

answers to this question.

Response:

A. Billing plans

B. Internal activity

C. External activity

D. Periodic processing

Browse 234 Q&As
Questions 17

Which type of billing is generally used in plant engineering and construction projects? Please choose the

correct answer.

Response:

A. Periodic billing

B. Project billing

C. Milestone billing

D. Fixed billing

Browse 234 Q&As
Questions 18

In which type of settlement the costs of all the periods up to the one you specify in settlement are settled?

Please choose the correct answer.

Response:

A. Periodic settlement

B. Full settlement

C. Profile settlement

D. Overview settlement

Browse 234 Q&As
Exam Code: C_TPLM22_64
Exam Name: SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4
Last Update: Mar 17, 2025
Questions: 234 Q&As

PDF

$49.99

VCE

$55.99

PDF + VCE

$65.99