Quality Control activities are what type of cost in the Cost of Quality concept?
A. Product Cost
B. Appraisal Cost
C. Preventive Cost
D. Failure Cost
The advantage of the Earned Value approach is that it allows the early detection of slippage by using an industry standard approach to:
A. Measure a project's actual progress
B. Forecast both project completion date and final cost
C. Track schedule and budget throughout the project life cycle
D. All of the above
E. None of the above
A standard must be:
A. Measurable, Achievable, and Robust
B. Measurable, Attainable, and Critical
C. Approved, Available, and Attainable
Which of the following represents the correct combination of Process Categories?
A. Management Processes, Work Processes, and Check Processes
B. Process Control, Product Control, and Environment Control
C. Quality Process, Management Process, and Customer Process
Which process measure focuses on how well the product or service performs in the customer environment?
A. Process Measure
B. Output Measures
C. Outcome Measures
D. Community Measures
Which of the following prescribes a format for Balance Sheets?
A. Business Partner
B. Generally Accepted Accounting Principles (GAAP)
C. Customers
D. Financial Accounting Standards Board (FASB)
Given the following sets (a-e), and their symbols (1-5), which one of the following best pairs the two sets? a ?Processes b ?External Entity c ?Data Stores
d ?Flows e ?Data Elements 1 - Parallel Lines 2 - Circles 3 - Arrows 4 - Rectangles 5 - Labels on arrows
A. c1, a2, d3, b4, e5
B. c2, a1, d4, b5, e3
C. c5, a3, d4, b2, e1
D. c4, a1, d3, b2, e5
The final product of the Pre-Requirements Analysis phase is the:
A. Feasibility Study
B. Preliminary Benefit Estimate
C. Preliminary Scope Statement
D. Requirements Definition
The challenge(s) of using the iterative development methodology is/are:
A. Real projects rarely follow the sequential flow
B. At the beginning of most projects there is often a great deal of uncertainty about requirements and goals
C. It is often a long time into development cycle before any functionality is available for customer review
D. All of the above
E. None of the above
Which of the following is NOT an Agile Development Methodology?
A. SCRUM
B. Extreme Programming
C. Prototype
D. Kanban
Structural Testing is also referred to as:
A. White Box Testing
B. Black Box Testing
C. Functional Testing
D. User Acceptance Testing
A program validates a numeric field as follows:
Values less than 10 are rejected, values between 10 and 21 are accepted, values greater than or equal to
22 are rejected.
Which of the following input values covers the MOST boundary values?
A. 9, 10, 11, 22
B. 9, 10, 21, 22
C. 10, 11, 21, 22
D. 10, 11, 20, 21
When planning a site visit to evaluate software your organization is considering purchasing, who should be on the site visit team?
A. SME, IT Support Team, Tester, BA
B. SME, Tester, BA
C. PM, Tester, BA
D. SME, IT Support Team
-- Exhibit -
-- Exhibit -The diagram is what type of chart?
A. Flow Chart
B. Pert Chart
C. Pareto Chart
D. Control Chart
E. Root Cause Analysis Chart