Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)

A. Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule

B. Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate

C. Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule

D. Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule

E. Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule

Browse 91 Q&As
Questions 5

Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement. (Choose the best answer.)

A. Accounting Method

B. Journal Rules

C. Supporting References

D. Accounting Rule

E. Mapping Sets

Browse 91 Q&As
Questions 6

Which two attributes are available while enabling a task as a business object for social networking?

A. Task

B. Project Number

C. Task Number

D. Creation Date

E. Project

Browse 91 Q&As
Questions 7

You have four resources in your organization: P, Q, R, and S.

Resource P - Project or resource calendar is active.

Resource Q - Project resource request dates are within the project or resource calendar effective dates.

Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.

Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.

Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)

A. P

B. Q

C. R

D. S

Browse 91 Q&As
Questions 8

While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. (Choose two.)

A. You used Create Tree in the action menu.

B. You used Create Tree Version in the action menu.

C. You used View Tree Version in the action menu.

D. You selected the Edit icon for opening the hierarchy.

E. You opened the hierarchy by clicking the name.

Browse 91 Q&As
Questions 9

In a Project Draft Invoice preview, quantity (hours) and unit price (bill rate) are shown as fields on the invoice. Quantity and unit price are then used to calculate the line total, then the total price of the invoice. After the invoice is transferred or

created in Receivables, the invoice detail has a quantity of 1, and a unit price equal to the line total. The detailed Unit Price/Quantity does not come through on the Receivables invoice.

Identify the correct statement about details in the receivables invoice. (Choose the best answer.)

A. The project sends only the invoice header and invoice line description to Receivables, not the invoice distributions.

B. The project sends the invoice header, invoice line description, and the invoice distributions to Receivables.

C. The project sends only the invoice header to Receivables, not the invoice line description and distributions.

D. The project sends the invoice line description and the invoice distributions to Receivables, but not the invoice header.

Browse 91 Q&As
Questions 10

Your customer wants to perform billing based on the Percent Spent invoice method. Identify two setups that are required in project contracts for calculating invoice amounts as per their requirement. (Choose two.)

A. billing events

B. bill plan

C. expenditure items

D. billing controls

E. invoice method

Browse 91 Q&As
Questions 11

Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016. Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)

A. The current period start date is used for calculating labor demand for the current year.

B. The current date is used for calculating labor demand for the current year.

C. The project start date of Jan-2015 was used for calculating labor demand, and hence it calculated the demand for the year 2015.

D. The date entered by a user as a parameter when running the Update EPS job was set to 01-Jan- 2015, and hence the calculations show results for the year 2015.

Browse 91 Q&As
Questions 12

Which product offering enables non-exclusive relationships between multiple projects and tasks with contracts and contract lines? (Choose the best answer.)

A. Project Contract-based costing

B. Project Contract-based billing

C. Project Contract Collection Center

D. Contract Team Connect

Browse 91 Q&As
Questions 13

Identify three correct statements about project types. (Choose three.)

A. Project type can be used as a source in subledger accounting.

B. Project type can be enabled for both billing and capitalization.

C. Summarization options can be specified at project type.

D. Classifications can be assigned at project type.

E. Project type can be associated with multiple project units.

Browse 91 Q&As
Questions 14

Which application generates external roles to grant both function and data security? (Choose the best answer.)

A. Authorization Policy Manager

B. Oracle Identity Manager

C. Business Process Manager

D. Functional Setup Manager

Browse 91 Q&As
Questions 15

Using Oracle Time and Labor, your client wants to put in a validation process that allows only a certain number of maximum hours an employee can charge in a day, and a minimum of hours he or she can report in a week. What feature would you use to meet this requirement? (Choose the best answer.)

A. project time validation rules

B. time calculation rules

C. time entry rules

D. time audit rules

Browse 91 Q&As
Questions 16

You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error. Identify two reasons for this problem. (Choose two.)

A. The corresponding Oracle Payables Cloud accounting period has not been closed.

B. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.

C. Pending burden summarization items have not been processed.

D. Unaccounted transactions are not imported.

E. Unaccounted transactions have not been swept to the next period.

Browse 91 Q&As
Questions 17

Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud,

but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.

What are three conditions for new employees to show up in the list? (Choose three.)

A. Current date is before the effective date of the resource, and you did not enable the "Include people with future-dated effective start dates" option during the search.

B. All new employees created as persons must have an active supervisor.

C. All new employees created as persons must be assigned to a department.

D. All new employees created as persons must have an active assignment.

E. All new employees created as persons must have an active project role.

Browse 91 Q&As
Questions 18

Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)

A. Receipt Accounting

B. Payables

C. Fixed Asset

D. Purchasing

Browse 91 Q&As
Exam Code: 1Z0-1057-22
Exam Name: Oracle Project Management Cloud 2022 Implementation Professional
Last Update: Mar 17, 2025
Questions: 91 Q&As

PDF

$49.99

VCE

$55.99

PDF + VCE

$65.99