Identify two formats available in the Capacity Planning chart.
A. Stacked histogram
B. Pie
C. Area
D. Variance
E. Cost
The Open Requests for Resource's portlet lists unstaffed assignments involving roles on the selected role team. Identify two ways that the portlet display can be organized.
A. Role by Project
B. Role by Resource
C. Project by Role
D. Resource by Project
E. Resource by Role
Identify three best practice uses of Notebook topics.
A. To document processes
B. To explain a constraint
C. To send out an email alert
D. To explain baseline update
E. To change user access
F. To update actual costs
G. To provide status information
Identify two benefits of customizing user-interface views.
A. Limit user access to functionality
B. Lock down security privileges
C. Administer users in the web interface
D. Target application functionality
E. User-based configuration
Where are risk response plans captured?
A. In the Risk Scoring Matrix
B. In the Activity Notebook for Risk
C. In the Risk Register
D. In the Project Notebook for Risk
Identify the best definition of the EPS.
A. The hierarchical definition of project budgets and actual costs.
B. The hierarchical definition of reporting structures.
C. The hierarchical structure of the security for projects.
D. The hierarchical structure of the database of projects.
You are an application administrator. You received a change request to alter the relationship between an EPS node and its associated OBS element.
What would be a prudent course of action to complete before moving forward with this change?
A. Merge the old OBS element with the requested OBS element.
B. Create a new OBS element per the change request.
C. Determine which users would be affected.
D. Delete the old OBS element per change request.
An activity is to be completed within a fixed time period and the total effort is also fixed. What duration type should be used?
A. Fixed Units
B. Fixed Duration and Units/Time
C. Fixed Units/Time
D. Fixed Duration and Units
Cost accounts are hierarchical, and___________.
A. are assigned in the project details
B. are created and managed at the project level
C. are applicable to all projects in the EPS
D. are assigned to users with security
You are a project manager on a fixed-bid contract. This contract has actually been positioned as a "loss leader" within your company because it is your first contract with this customer. The hope is that you can prove yourself to the customer and win additional business at higher margins down the road. The margins for this contract are very slim.
What would be the best solution to set up in P6 to give you the visibility that you need to minimize the probable financial loss?
A. Set a Mandatory Finish constraint at each contractual milestone and track schedule performance against the constraint.
B. Set all activities in your project plan to Physical % Complete, and use Remaining Duration to track schedule performance.
C. Set all activities in your project plan to Units % Complete, and use Remaining units to track schedule performance
D. Set a Must finish By date at the project level, and track schedule performance using float in the project plan.
Identify the true statement regarding the EPS page in P6 R8.
A. You can copy a project on the EPS page and paste it into another EPS node.
B. You cannot copy projects on the EPS page - this must still be done in the Client.
C. Any user can now copy projects on the EPS page regardless of the user's Security profile.
D. Only application administrators have the privilege to copy/paste projects.
You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?
A. Your security does not allow you to update Activity Status.
B. You did not save the changes made to the activities.
C. You have not completed each of the activity steps.
D. You must refresh the view in the web to view the changes.
You are creating a new portfolio scenario. You are attempting to save it for all users, but the selection is unavailable (grayed out).
What is the cause?
A. You have insufficient global security privileges.
B. You have Insufficient project security privileges.
C. You have insufficient portfolio security privileges.
D. You have insufficient user security privileges.
Select the true statement regarding project security profiles.
A. Project security profiles define the weight of project codes.
B. To receive a project security profile, a user must be defined as a resource.
C. Project security profiles override global security profiles.
D. To access projects, a user must be assigned a project security profile.
The two global profiles that are hard-coded in the system and cannot be deleted or changed _________ and _________.
A. Project Manager
B. System Administrator
C. IT Administrator
D. Admin Super User
E. Resource Manager
F. No Global Privileges